awards Rehabilitation of the Old Terminal Building at the Albuquerque International Sunport

Date of Completion: 2002

Building Area:
16,871 gross square feet

Contractor:
T. A. Cole and Sons, Inc. (Phase I)
Telstar Construction Co. Inc. (Phase II)

This project was a historic "rehabiltation." We worked closely with the State Historic Preservation Office and the Landmarks and Urban Conservation Commission in order to return the building to it's 1942 status which included the air side patio, portal, and restoring the public interior areas of the Great Hall and Dining Room. Ramps were added to the building exterior in accordance with ADA. The building interior was also rehabilitated to include ADA accessibility in the restrooms an elevator was added between the 2nd floor and basement. New supply air vents were hidden behind beams on either side of the Great Hall. New fan coil units were hidden behind grills that formerly hid radiators.